Scope:

This project consists of channel improvements and the construction of multiple bridges and bridge-class culvert crossings between FM 78 and Ackerman Road along West Tributary to Rosillo Creek. Bridges will be built along Old Seguin, Binz-Engleman, and Ackerman roads. Culvert crossings will be built along Starfire, Redding, and Kirby roads. Channel improvements will extend from FM 78 to Ackerman Road along West Tributary to Rosillo Creek. Approximately 160 adjacent properties will be removed from the 1% annual chance (100-year) storm event floodplain due to planned improvements and floodplain remapping. In addition, unflooded access will be provided at six roadway crossings during a 1% annual chance storm event.

Project Documents:

Post Construction Vision Exhibit

Construction Updates:

Binz-Engleman and Kirby Drive are complete.  The Contractor is working on the second half of the bridge on Ackerman Road and is working on new box culverts on Starfire Road.

The contractor is completing the rip rap on the channel.  Final overlay on Redding is scheduled for Tuesday, September 6, 2016.

 
 
Precinct
City
Watershed
Creek
Project Type
4
Kirby
Salado Creek
West Tributary to Rosillo Creek
Natural Waterway Conveyance

Precinct
4

City
Kirby

Watershed
Salado Creek

Creek
West Tributary to Rosillo Creek

Project Type
Natural Waterway Conveyance
 

Previous Meetings

February 15, 2017

October 25, 2012

January 24, 2012

October 20, 2011

February 8, 2011

October 11, 2010

August 19, 2010

November 4, 2009

 

Comments & Questions Form