Find the latest news, updates and announcements relating to Bexar County Flood Control Capital Improvement Projects.
> Rock Creek NWWC/Outfall Phase II
Bexar County Flood Control Projects
Rock Creek NWWC/Outfall Phase II (SA 6)
print version comment
|
|
The scope of this project is to improve drainage conditions of Rock Creek between Callahan Road and Loop 410. The project is intended to improve the existing channel to allow for better drainage and efficient water flow for Rock Creek.
Upcoming Meetings
There are no upcoming meetings. Check back soon.
Consultant:
Land Design Partners, Inc.
Contractor:
TBD
Construction Cost:
$3,000,000 (estimated)
Advertise:
March 2015 (estimated)
Construction Start:
June 2015 (estimated)
Construction End:
June 2016 (estimated)
Land Design Partners, Inc.
Contractor:
TBD
Construction Cost:
$3,000,000 (estimated)
Advertise:
March 2015 (estimated)
Construction Start:
June 2015 (estimated)
Construction End:
June 2016 (estimated)
Project Status
Inactive
On Hold
| Project Initiation |
Preliminary Design |
Detailed Design |
Construction | Project Complete |
| project status | project status | project status | project status | project status |
| Precinct | City | Watershed | Creek Name | Project Type |
|---|---|---|---|---|
| 3 | San Antonio, District 8 | Upper San Antonio River | Rock Creek | Natural Waterway Conveyance |