Bexar County Flood Control Projects

Find the latest news, updates and announcements relating to Bexar County Flood Control Capital Improvement Projects.

Boerne Stage Road (LC 18)

print version comment

Scope:
This project involves reconstructing Borne Stage Road, from Cross Mountain Trail to the frontage road of IH10, and elevating the roadway out of the 25-year ultimate floodplain. The roadway design includes one 12 ft travel lane in each direction, a 14 ft center turn lane, and 6 ft shoulders.  Improvements to the adjacent Leon Creek are also included in the project.

 

 

Upcoming Meetings There are no upcoming meetings. Check back soon.

Consultant:
AECOM

Contractor:
TBD

Construction Cost:
10,800,000 (estimated)

Advertise:
Summer 2012 (estimated)

Construction Start:
Fall 2012 (estimated)

Construction End:
Summer 2013 (estimated)

Project Status


Inactive

On Hold

Project
Initiation
Preliminary
Design
Detailed
Design
Construction Project
Complete
project status project status project status project status project status

Precinct City Watershed Creek Name Project Type
3 Outside City Limits Leon Creek Leon Creek Low Water Crossing


Previous Meetings


Boerne Stage Road Public Meeting


Venue: Leon Springs Baptist Church | Date: 2009-10-01 | Contact: info@bexar.org




Boerne Stage Road Public Meeting


Venue: Leon Springs Baptist Church | Date: 2008-05-06 | Contact: info@bexar.org