Rosillo Creek RSWF (SC 15)

print version comment

Scope:
This project consists of channel improvements and the construction of multiple bridges and bridge-class culvert crossings between FM 78 and Ackerman Road along West Tributary to Rosillo Creek.  Bridges will be built along Old Seguin, Binz‐Engleman, and Ackerman roads.  Culvert crossings will be built along Starfire, Redding, and Kirby roads.  Channel improvements will extend from FM 78 to Ackerman Road along West Tributary to Rosillo Creek.  Approximately 160 adjacent properties will be removed from the 1% annual chance (100-year) storm event floodplain due to planned improvements and floodplain remapping.  In addition, unflooded access will be provided at six roadway crossings during a 1% annual chance storm event.

Project Documents:
Post Construction Vision Exhibit

Construction Updates:
Ackerman Road construction has started, including channel work, clearing, and utility relocations.


Upcoming Meetings There are no upcoming meetings. Check back soon.

Consultant:
IDS Engineering Group

Contractor:
Shannon-Monk, Inc.

Construction Cost:
$7,616,849.40

Advertise:
June 2012

Construction Start:
February 2013

Construction End:

May 2015 (estimated)

Project Status


Inactive

On Hold

Project
Initiation
Preliminary
Design
Detailed
Design
Construction Project
Complete
project status project status project status project status project status

Precinct City Watershed Creek Name Project Type
4 Kirby Salado Creek West Tributary to Rosillo Creek Natural Waterway Conveyance


Previous Meetings


Kirby City Council Meeting


Venue: Kirby City Hall | Date: 2012-10-25 | Contact: info@bexarfloodcontrol.org




Rosillo Creek Community Meeting


Venue: Kirby City Hall | Date: 2012-01-24 | Contact: info@bexarfloodcontrol.org




Kirby City Council Meeting


Venue: Kirby City Hall | Date: 2011-10-20 | Contact: info@bexarfloodcontrol.org




Rosillo Creek Community Meeting


Venue: Kirby City Hall | Date: 2011-02-08 | Contact: info@bexarfloodcontrol.org




Rosillo Creek Community Meeting


Venue: Kirby City Hall | Date: 2010-10-11 | Contact: info@bexarfloodcontrol.org




Kirby City Council Meeting


Venue: Kirby City Hall | Date: 2010-08-19 | Contact: info@bexarfloodcontrol.org




Kirby City Council Meeting


Venue: Kirby City Hall | Date: 2009-11-04 | Contact: info@bexarfloodcontrol.org