Bexar County Flood Control Projects

Find the latest news, updates and announcements relating to Bexar County Flood Control Capital Improvement Projects.

Sixmile Creek Drainage Improvements - S. Flores Bridge (SA 43)

print version comment

Scope:
The overall scope for this project includes the analysis of Sixmile Creek starting downstream of Roosevelt Avenue and continuing upstream to IH35. The overall project will entail channel and bridge improvements between Hutchins Place and Roosevelt Avenue to reduce the structural flooding along Six Mile Creek. The intent of the project is to reduce the floodplain in the residential areas and provide for unflooded access across South Flores during the 100-year ultimate development storm event.  This segment of the project is to reconstruct the existing roadway and bridge at South Flores Street and Sixmile Creek.  The project limits are Deely Street (north) and approximately 300’ north of the South Flores and Roosevelt intersection (south).

Construction Updates:
The project is substantially complete and open to traffic.






Upcoming Meetings There are no upcoming meetings. Check back soon.

Consultant:
CDM Smith

Contractor:
Capital Excavation Company
 
Construction Cost:
$2,518,888.99

Advertise:
November 10, 2011

Construction Start:
February 23, 2012

Construction End:
February 28, 2012

Project Status


Inactive

On Hold

Project
Initiation
Preliminary
Design
Detailed
Design
Construction Project
Complete
project status project status project status project status project status

Precinct City Watershed Creek Name Project Type
1 San Antonio, District 3 Upper San Antonio River Sixmile Creek Regional Drainage Improvements


Previous Meetings